Now we are seven and all systems are go. Click http://www.stockbridgeupdates.com and in upper right corner, subscribe or leave us a comment. Find our complete archive from the first issue in August 2020 through April 15, 2026. Search an old article, read or reread them, and of course, take another look at all those fabulous photographs. if you would like to support Stockbridge Updates, go to VENMO @carole-owens-6 (no caps) or mail a check to P. O. Box 1072, Stockbridge, MA. 01262. If you like this issue, pass it on.

Notes from the Stockbridge Fire House Planning Committee

A working group met separately from the Committee and reported as follows:

  1. Developed space/function design to determine square footage. The estimated square footage based on functions is 20,000 to 20, 600 square feet.
  2. An assessment of the feasibility of the site based on the size of the building necessary
  3. Four sites have been suggested.

Using 4 designs – 2 one story and 2 two-story layouts, one site on Gleandale Riad was considered not feasible and the second on Glendale Road was considered feasible. The DPW site was considered optimum, and the The Industrial Park site would be considered only as a “default”

Of the 4 building designs proposed, the ones that allow drive through for large trucks rather than backing up were preferrable. Two-story buildings used and disturbed less land. Primary focus will be on the DPW site unless a serious obstacle is encountered.